Case Studies

Why the Same Brantford Project Used Two Completely Different Installation Methods

Last updated: September 5, 2026

One rural Brantford property, two window openings, and two very different installation calls made on the same day.

Same house, same day, same crew, two openings finished in completely different ways. A dated 6-section bow window on this rural Brantford property was replaced retrofit, working entirely within its existing wood surround. A single slider window a few feet away, right beside the new steel entry door, was torn out completely and rebuilt stud-to-stud. Neither decision was arbitrary. Each opening got assessed on its own condition, not treated as part of a single blanket "how we do windows" policy.

What actually made the bow window a retrofit candidate

The bow window's original wood surround and base had held up structurally, no rot, no significant moisture damage, sound enough to build the new window system on top of rather than tear out. That's the actual test for whether retrofit is the right call, not a default preference for the cheaper or faster option. Ontario's building code requires window installation to conform to CSA A440.4 under Article 9.7.6, and that standard applies whether the job is retrofit or full-frame; what changes is what the installer is building the new assembly onto. Here, the existing structure passed that test.

Before and after of a Brantford bow window replacement — a dated dark wood curved bow window on the left, a new white vinyl six-section bow window on the right
Before and after: the dated dark wood bow window, and the finished white vinyl six-section replacement.

The prep work retrofit still requires

Retrofit doesn't mean dropping a new window into an untouched opening. The existing wood posts dividing the original bow window's sections had to be cut back first to properly accommodate the new frame profile, a 3¼" system in this case. Skip that step and a retrofit ends up with gaps at the mullions and an uneven reveal, exactly the kind of result that gives retrofit installation a bad reputation it doesn't deserve when it's done properly.

Two frame thicknesses, one reason for both

The finished bow window uses six sections in a true curved configuration, not the three flat angled panels of a bay window. The two outer sections are casement windows built with a thicker frame profile to house the crank hardware and hinge mechanism. The four inner sections are picture windows, fixed and non-operable, using a thinner frame because there's no hardware to accommodate. That frame-thickness difference isn't a manufacturing inconsistency between the sections, it's a direct, deliberate reflection of which sections actually open.

Why the slider a few feet away needed the opposite approach

The single slider window beside the entry door didn't pass the same test the bow window did, so it went stud-to-stud: removed completely down to the framing rather than built on top of what was already there. On a semi-rural property like this one, openings can age at very different rates depending on their exposure and original construction, which is exactly why a single "always retrofit" or "always full-frame" policy fails homeowners. The right call is opening-by-opening, not project-by-project.

Rebate note: Window and door replacements like this one may qualify for up to $100 per rough opening under the Home Renovation Savings™ program when you bundle two or more eligible upgrades. ENERGY STAR® certified products are required, and eligibility and approval depend on the current program requirements and administrator, with an energy assessment needed before work begins.

FAQ

Frequently Asked Questions

The same standard, CSA A440.4 under Article 9.7.6, applies to both methods. What differs is what the installation is being built onto, an existing sound structure for retrofit, or new framing and sealing from scratch for a full stud-to-stud rebuild.
Operable sections like casement windows need a thicker frame profile to house the crank mechanism and hinge hardware. Fixed picture window sections have no such hardware, so they can use a thinner frame profile and a slimmer visible sightline.
Yes. Each window opening should be assessed individually based on its own condition and exposure. A sound opening is a good retrofit candidate, while an opening with structural or moisture issues typically needs a full stud-to-stud rebuild, even within the same overall project.

Explore More

Keep exploring what Trust Build can do for your home

Free Quote

Have windows that might need different approaches?

Not every window on a home needs the same installation method, and assuming otherwise can mean overpaying for some openings or underserving others. Every Trust Build installation is completed by our own in-house crews and backed by a lifetime transferable warranty, with 0% financing available.

  • Detailed project assessment
  • Written itemized quotation
  • Product and installation recommendations
  • Financing options available

Get Your Free, No-Obligation Quote

Tell us a little about your project and we'll get back to you. Takes under a minute — no pressure, no pushy calls.

By requesting a quote you agree to be contacted about your request. We never share your info or send spam.

Join 8,700+ Ontario homeowners · Energy Star products · Lifetime transferable warranty